January 2017 Capital Project Update
 
 
 
 
 
 
 
 
 
 
Lindbergh Capital Project Construction  
 
Lindbergh Capital Project Construction  
 
 Lindbergh Capital Project Construction
 
 Lindbergh Capital Project Construction
 
Adams Field
 
Adams Field
 
July 19, 2016 Update
 
Franklin Elementary & Middle School Exterior Windows 
  • The contractor is gearing up to start installation of windows at the Franklin Complex. Nearly 80 new windows will be installed during the summer of 2016 at Franklin Elementary and Middle Schools. The remaining 350 windows will be installed in the summer of 2018. Window delivery for the 2016 windows is scheduled to arrive in early July 2016. 
Herbert Hoover Elementary & Middle Schools Exterior Windows 
  • The contractor is gearing up to start installation of windows at the Hoover Complex.  Nearly 200 new windows will be installed during the summer of 2016 at Hoover Elementary and Middle Schools. The remaining 340 windows will be installed in the summer of 2017. Window delivery for the 2016 windows is scheduled to arrive in early-July 2016. 
Adams Field 
  • A tremendous amount of work took place at the Adams Field Complex during the month of June. Demolition has begun in the Field House, with ADA upgrades being made to the locker rooms. Demolition of the visitor side bleachers, removal of track and natural turf field were also completed during the month. A conduit for new fiber was started from Franklin Middle to the Field House and Press Box. As the end of the month approached the contractors were able to start with the underground drainage beneath the new artificial turf field and the site. All work at the Adams Field Complex is on schedule. 
  • At completion, the new complex will include a new artificial turf field, new eight-lane track, sports lighting, addition bleachers, renovations to the Press Box, new scoreboards, ADA renovations to the Athletic Field House, and an addition to the Athletic Storage Building. Information technology upgrades are also being made to the Athletic Complex. All work is scheduled to be completed and turned over to the district in mid-October 2016. 
Kenmore East High School  
  • Technology Room and Computer Room upgrades began in June 2016. Hazardous material removal started and as with many older buildings, multiple layers of flooring and ceilings have been discovered and were removed. Mechanical, electrical and plumbing demolition were started in preparation for the new gymnasium addition. All work at Kenmore East High School is on schedule.  
Kenmore West High School 
  • The new guidance suite upgrades began in June 2016.  Hazardous material removal and demolition started and will continue through the early part of July throughout the entire building. Work also began with the removal of auditorium seating. The bus loop and parking lot were also laid out in preparation of work beginning in early July. All work at Kenmore West High School is on schedule. 
Lindbergh Elementary School  
  • The bus loop was started during the month of June 2016 at Lindbergh Elementary. Once complete, the bus loop will relieve the congestion of traffic from the Irving Terrace entrance of the building. Although six trees had to be removed to allow for the new bus loop to be installed, eight new trees will be planted. All work at Lindbergh Elementary is on schedule. Additional work in the building will continue once the summer 2016 push has been completed.
 
July 7, 2016 Update
 
As part of the Ken-Ton School District Phase 2 Capital Project, which was approved by voters in December 2014, new bus loops are currently under construction at Lindbergh Elementary School and Kenmore West High School.
 
The purpose of the bus loops is to address long-standing traffic and safety concerns at both locations and to accommodate additional buses that will be needed as a result of the Scenario I consolidation transition and lower mileage eligibility limits.
 
The Ken-Ton School District is committed to preserving as many trees and as much green space as possible. All trees/memorials that must be displaced as a result of the construction of the new bus loops will be moved/replaced. The following diagrams show the current and planned layout at both schools, including the types of individual trees that will be planted:
 
Lindbergh Elementary School:
 
 Lindbergh Tree Plan
 
Kenmore West High School:
 
 KW Tree Plan
 
 
June 20, 2016 Update 
 
 Capital Project Groundbreaking  
 
In May 2016, there was a significant increase in construction-related activities with the beginning of the construction phase of the Phase 2 Capital Project. Summer 2016 will be a busy season for the Kenmore Town of Tonawanda Union Free School District, with work ongoing at multiple sites throughout the district.

The following is an update on only those projects that are scheduled to begin in June.

Franklin Elementary & Middle School Exterior Windows at Franklin Elementary, Hoover Elementary, Franklin Elementary and Hoover Middle:

  • A majority of exterior windows at Franklin Elementary/Middle School and Hoover Elementary/Middle School will be replaced during the 2016, 2017 and 2018 summer breaks.

Adams Field:

  • The work at the Adams Field complex includes a new artificial turf field, new eight-lane track with steeple chase, long/triple jump pits, high jump, pole vault, shot put, sport lighting, addition bleachers, renovations to the press box, new scoreboards, ADA renovations to the Athletic Field House, and an addition to the Athletic Storage Building. Information technology upgrades are also being made to the complex. All work is scheduled to be completed in mid-October.

Kenmore East High School:

  • The work at Kenmore East High School includes a new two-story addition for gymnasium, locker rooms, fitness and mechanical rooms, reconstruction of the first-floor fitness room into new technology room and computer rooms, ADA renovations to existing bathrooms, renovations to the auditorium and stage, upgrade of existing computer labs, and miscellaneous HVAC, electrical plumbing and information technology work throughout the entire building. All work is scheduled to be completed in December 2017.

Kenmore West High School:

  • The work at Kenmore West High School includes a replacement of fourth-floor lockers, a new bus loop/drop off, first-floor guidance suite, computer lab upgrades, ADA renovation to existing bathrooms, and renovation of the second-floor guidance offices into three new classrooms. All work is scheduled to be completed in September 2017.  The exterior field work at Kenmore West High School is scheduled to be completed in September 2017.

Thomas Edison Elementary School:

  • The work at Edison Elementary School includes the replacement of the existing gymnasium folding partition and installation of new safety devices, replacement of miscellaneous interior doors and frames, ADA upgrades in the auditorium, boys and girls locker and toilet rooms, and faculty toilet room, upgrades to the kitchen, information technology upgrades throughout the entire building, and miscellaneous plumbing, mechanical, and electrical upgrades in the entire building. All work is schedule to be completed in September 2017.

Lindbergh Elementary School:

  • The work at Lindbergh Elementary includes replacement of the existing gymnasium folding partition and installation of new safety devices, installation of new gymnasium ceiling lights, replacement of miscellaneous interior doors and frames, ADA upgrades in the auditorium, boys and girls locker and toilet rooms, and faculty toilet room, information technology upgrades throughout the entire building, and miscellaneous plumbing, mechanical, and electrical upgrades in the entire building. All work is schedule to be completed in September 2017.  In addition to the interior work, a new bus loop is being added at the Irving Street entrance with replacement of trees displaced by the work scheduled.  The memorial tree will be replaced in a new location in the front, and the memorial garden will remain unaffected. This work is scheduled to be completed by September 2016.

 